What should you watch out for when upgrading a project to TIA Portal V14? (Order of compilation with controllers and operator panels)

  • Entry
  • Associated product(s)
Pay attention to the order of compilation after updating TIA Portal V14 projects.

Instructions
After project upgrade to TIA Portal V14 you get the message below.

"To finish upgrade of project, select the menu command "Edit > Compile" for each device in the project."



Fig. 01

Here you should observe the following order of compilation:
  1. Controllers
  2. Operating panels

Background
The procedure ensures that the controller data required for compiling the operator panels is available (system diagnostics, for example)

Additional Keywords
0604:000342



Security information
In order to protect technical infrastructures, systems, machines and networks against cyber threats, it is necessary to implement – and continuously maintain – a holistic, state-of-the-art IT security concept. Siemens’ products and solutions constitute one element of such a concept. For more information about cyber security, please visit