SIMOGEAR, 2KJ1/2KJ3: Checking the pressure breather valve

  • 文档
  • 涉及产品
How is the pressure breather valve checked and activated?

Check that the pressure breather valve is activated.

If the pressure breather valve has a transport fixture, then this must be removed before commissioning.

Remove the transport fixture by pulling the securing clip 1 in the direction of the arrow.


Note: Applay also to the gearbox BA 2030