7/30/2014 6:29 PM | |
Posts: 8 Rating:
|
Hello, I solve the problem when I demokufr with SINAMICS S110 servo motor SIMOTICS S 1FK7 (see kufr.jpg). The drive works in service and at the same time positioning during a power outage occurs and I need to rebuilt the servomotor to the zero position. In the manual I found, as established standard telegram 111 (see ST111.jpg) and for my case, I focused on control words POS_STW2 (see POS_STW2.jpg) and STW2 (see STW2.jpg). What I had in these control words to set that during a power outage servomotor rebuilt to zero position? Thank you in advance for your answer Regards Tomas AttachmentPictures.zip (174 Downloads) |
8/1/2014 9:21 AM | |
Posts: 8 Rating:
|
Hi, I need the actuator during a power outage turned to the reference point. Thank you for your understanding
Attachmentpictures.pdf (157 Downloads) |
8/1/2014 9:13 PM | |
Posts: 8 Rating:
|
Hi, let me ask otherwise. What is generally uses the control word STW2 (see STW2.jpg)? Thank you in advance for your answer |