Good day, I have a s1200 PLC firmware 4.2.1, and the code on it is in v13. am I correct in saying that if I want to update the version to v15 tia, that I will open the v13 code in v15, itll do the update/upgrade of the code and then I simply download that code onto the plc again? my concerns are,
Im currently working at a big factory and they have many siemens PLCs and every second one needs a different TIA version to upload the code and make any changes as they dont have back ups for many of the stations, my plan is to get most if not all of them on the same version of TIA, to make it much better to do work there and fault find in the future. ------------------------------------------------------------------------------------------ |
Last edited by: Jen_Moderator at: 10/19/2023 11:05:42New subject after splitting |
|
| 10/19/2023 4:09 PM | |
|
Joined: 9/3/2008 Last visit: 1/5/2026 Posts: 947 Rating:
|
Hi To upgrade your V13 projekt, you need your project to be TIA V13 SP1 or later. |
|
Michael |
|