Hi Oreca, I have a PCS7 system version 6.0 and I need upgrade from V6.0 to V8.1. Whic way is correct for me? How can I upgrade from V6 to V8.1, ? Ex: 6.1->7.2->8.1 or any think? Thanks ------------------------------------------------------------------------------------------ |
Last edited by: Min_Moderator at: 5/17/2016 11:29:44 AMNew subject after splitting |
|
5/23/2016 1:54 PM | |
Joined: 5/27/2014 Last visit: 11/3/2023 Posts: 81 Rating: (11) |
Hi Eng, as I know you have to update your PCS 7 to Version 7.1 SP4 first:
Regards |
Last edited by: Heisenberg___ at: 5/23/2016 1:58:32 PM |
|
6/21/2016 3:46 AM | |
Joined: 5/26/2011 Last visit: 1/10/2024 Posts: 455 Rating: (7) |
Hello Heisenberg, I found another version of that v6 to v7.1 upgrade manual that says "without utilization of new function", what should I follow if I am to update to v8 from v6.1? My project is using CEMAT (Holcim). I found the CEMAT upgrade package (which would contain the CEMAT blocks and faceplat right?) saying I can update from v6.1 directly to v8 (6DL5430-8AX18-0XE0) . Does this mean I don't have change anything in the program (no need for any block update) until I have v8 where I do the CEMAT block update (will still have the CEMAT v6 by this time)? Meaning I will only be updating license during the 2 steps software upgrade to from v6 to v7 and from v7 to v8? Thanks you so much. |