Dear Boletus, The customer has no concern on power saving as they don't use the national grid power supply while the sugar mill is in operation. When the mill is in operation, they have 2 x 30T steam boilers and they have their own electrical supply from steam turbines. It may like as others. The mill is only operating for 3 months out of a whole year due to availability of raw materials (sugarcane). I am reading now the Braking Chopper Operation Guideline and feel like G120 + Braking Resistors solution still can be applicable. https://support.industry.siemens.com/cs/ww/en/view/22101908
|