8/7/2019 5:44 AM | |
Joined: 6/29/2015 Last visit: 8/15/2023 Posts: 11 Rating: (1) |
Hi Dear Colleagues, First of all thanks for sharing it was clarified more than ever. but I missunderstood one thing so there are two F-DQ (F-Q1 and F-Q2 ) controlling two contactor ant then these contcats drive to motor or whatever. first question is how to program in PLC I mean you used two feedback block and drive two different FQ via feedback blocks with same feedback or used just one feedback block and drive both FQs via the single feedback block. Actually I have made connection for each contactor to each F DQ I wonder how I manged in my program Best Regards Levent
------------------------------------------------------------------------------------------ |
Last edited by: Jen_Moderator at: 08/07/2019 07:02:40New subject after splitting |
|
8/7/2019 8:09 AM | |
Joined: 7/9/2015 Last visit: 1/14/2025 Posts: 4100 Rating: (617)
|
Hi LHotan, for your general question I can give you a recommendation to following manuals: SIMATIC Industrial Software SIMATIC Safety V13 - Getting StartedSIMATIC Safety - Getting StartedRegards, Towome |
|
|