4/16/2016 7:04 PM | |
Joined: 9/2/2012 Last visit: 8/15/2024 Posts: 711 Rating: (30) |
Dear Navnag, thank you for confirming more than 1 dp node is not an issue in the case of R-System. PAA start and end programmed correctly, also DP node details.. Kindly find the attached program herewith. Please have a look.. Kindly note that, since there are issue in the system, we have configured DB13,DB14 for communication just to check if any improvement. But NO is the answer.. AttachmentR_FORUM.zip (248 Downloads) |
|
|
4/16/2016 8:08 PM | |
Joined: 11/21/2007 Last visit: 9/25/2024 Posts: 2325 Rating: (308) |
Hello |
There is no such thing as the last bug in a program |
|
This contribution was helpful to1 thankful Users |
4/17/2016 9:45 AM | |
Joined: 11/21/2007 Last visit: 9/25/2024 Posts: 2325 Rating: (308) |
Hello Pl check out the the Manual : The Table on Page-11 indicates that it is suitable for Software Redundancy ( SWR ) |
There is no such thing as the last bug in a program |
|
This contribution was helpful to2 thankful Users |
4/17/2016 5:26 PM | |
Joined: 5/28/2008 Last visit: 10/4/2024 Posts: 4515 Rating: (839)
|
Hello, For each Rack, Please check that both IM153 have same part numbersm firmware version and relase no. in according to this note: New Revised Interface Module IM153-2 for ET 200M *
|
Ayman Elotaify |
|
This contribution was helpful to1 thankful Users |