Hello, The duration of a safety program can be estimated by using the S7cotia table (Excel sheet). The sheet can be downloaded here: http://support.automation.siemens.com/WW/view/en/25412441 You will see that the result is dependent of the CPU type. May be is a faster CPU the solution. In any case, try to reduce the size of the safety program to the strict safety related functions. |