10/27/2015 4:43 PM | |
Joined: 1/3/2009 Last visit: 6/30/2022 Posts: 161 Rating:
|
Hi all, My system has a redundant 412-5H CPU pair V6.0 and 6 ET 200M with IM 153-4 PN V4.0. I/O racks are connected in open ring configuration as per Siemens "system redundancy" reccomendation. However, I cannot correctly configure my system to start and work properly. Is there a step-by-step procedure to configure this system? I am attaching the project for reference (hw configuration only) Thank you in advance AttachmentProject.zip (229 Downloads) |
Stefano Angioni |
|
This contribution was helpful to
1 thankful Users |