3/11/2025 12:06 PM | |
Joined: 3/10/2025 Last visit: 8/11/2025 Posts: 5 Rating:
|
In my project, six 1513R-1 PN plcs are working separately as redundant in 3 different regions. Apart from these 3 regions, I have 2 Scada computers working as redundant. 4 regions are connected to each other with fiber cables. I want to select the switches of this system and make the network configuration.
AttachmentNetwork_F4.pdf (190 Downloads) |
3/11/2025 4:05 PM | |
Joined: 8/12/2021 Last visit: 8/20/2025 Posts: 351 Rating:
|
Hi! Sorry but, what is the question? About the topology or about the election of the switches? If it is to validate the installation, perhaps you should contact a trusted salesperson or use the TST. |
If this Information really helps, you could use the Rate function |
|